Summer Certification Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 4

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

A.

5

B.

2

C.

3

D.

4

Full Access
Question # 5

Which is an example of Administer Procurements?

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Full Access
Question # 6

The project manager is looking at a precedence diagram.... the duration of this task?

The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

What is the outcome of the duration of this task ' ?

A.

The task will be completed on time.

B.

The task will not be completed on time.

C.

Activity A is not a critical path task

D.

The precedence diagram cannot be used to provide answers for duration calculations

Full Access
Question # 7

What provides information regarding the ways people, teams, and organizational units behave?

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior

Full Access
Question # 8

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

A.

Bottom-up estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Parametric estimating

Full Access
Go to page: