Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 4

A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?

A.

Create a risk in the risk register for each S1 defect and assign actions.

B.

Consult the risk register and implement the risk response actions.

C.

Ask the developers to work longer hours and resolve the defects.

D.

Review the organizational chart to find out who else can sign off UAT.

Full Access
Question # 5

What process in Project Risk Management prioritizes project risks?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Responses

D.

Implement Risk Responses

Full Access
Question # 6

What should be the frequency for meetings when transitioning from Scrum to Kanban?

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

Full Access
Question # 7

Which sentence summarizes the salience model?

A.

Classifies stakeholders based on assessment ol Iheir power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Full Access
Question # 8

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Full Access
Go to page: