Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 4

The diagram below is an example of a:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Full Access
Question # 5

The total of the planned value (PV) is also known as:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Full Access
Question # 6

Which of the following is a tool and technique used in the Develop Schedule process?

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Full Access
Question # 7

Which process determines the risks that may affect the project and documents their characteristics?

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Full Access
Question # 8

In a project, total float measures the:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Full Access
Go to page: