Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 25

Which of the following is an example of an organizational system that is arranged based on the job being performed?

A.

Simple

B.

Multi-divisional

C.

Functional

D.

Project-oriented

Full Access
Question # 26

What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?

A.

Get expert judgment.

B.

Count on personal experience.

C.

Ask project sponsors.

D.

Delay the project until technical uncertainty is clarified

Full Access
Question # 27

Which input will be used when tasked with developing the human resource plan?

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Full Access
Question # 28

The individual or group that provides resources and support for a project and is accountable for success is the:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Full Access
Question # 29

Work performance information and cost forecasts are outputs of which Project Cost Management process?

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Full Access
Question # 30

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

A.

Cost management plan.

B.

Work performance information.

C.

Quality management plan.

D.

Work breakdown structure.

Full Access
Question # 31

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

A.

Enterprise environmental factors

B.

Work performance reports

C.

Organizational process assets

D.

Context diagrams

Full Access
Question # 32

A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.

How can the manager document the business value for the Portfolio Steering Committee?

A.

Conduct a feasibility study to determine the business impact of the new product.

B.

Prepare a benefits management plan to capture target benefits and strategic alignment.

C.

Execute a market study for similar products and demonstrate a market need.

D.

Create a presentation outlining the business benefits of the new product.

Full Access