Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 385

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

A.

Initiating Process Group

B.

Planning Process Group

C.

Executing Process Group

D.

Monitoring and Controlling Process Group

Full Access
Question # 386

In which type of organization does the project manager have the maximum influence

A.

Centralized

B.

Composite

C.

Simple Organic

D.

Multi-divisional

Full Access
Question # 387

Perform Quantitative Risk Analysis focuses on:

A.

compiling a list of known risks and preparing responses to them.

B.

assessing the probability of occurrence and Impact for every risk in the risk register.

C.

evaluating the contingency and management reserves required for the project.

D.

analyzing numerically the impact of individual risks on the overall project's time and cost objectives.

Full Access
Question # 388

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Full Access
Question # 389

What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?

A.

Project Management

B.

Program Management

C.

Portfolio Management

D.

Operations Management

Full Access
Question # 390

Which of the following documents ate created as part of Project Integration Management?

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Full Access
Question # 391

Which of the following is an example of an internal factor that influences the outcome of the project?

A.

Legal restrictions

B.

Financial considerations

C.

Commercial database

D.

Geographic distribution of facilities

Full Access
Question # 392

Which of the following tasks focuses on decomposing work packages?

A.

Adjust duration estimates

B.

Define activities

C.

Complete rolling wave planning

D.

Develop milestone list