Question # 385

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Full Access
Question # 386

To which process is work performance information an input?

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Full Access
Question # 387

The formal and informal interaction with others in an organization industry, or professional environment is known as:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Full Access
Question # 388

Who selects the appropriate processes for a project?

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Full Access
Question # 389

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

A.

-700

B.

-200

C.

200

D.

500

Full Access
Question # 390

What is the function of a Project Management Office (PMO)?

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Full Access
Question # 391

When is a project finished?

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Full Access
Question # 392

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Full Access