Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 337

After defining activities in project schedule management, which processes should a project manager follow?

A.

Sequence Activities and Estimate Activity Durations

B.

Estimate Activity Durations and Control Schedule

C.

Develop Schedule and Control schedule

D.

Review Activities and Develop Schedule

Full Access
Question # 338

Which enterprise environmental factors should be considered when creating a new procurement contract?

A.

Supply chains

B.

Trial engagements

C.

Lessons learned register

D.

Local laws and regulalk

Full Access
Question # 339

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.

What are the four elements of a RACI chart?

A.

Recommend, approve, coordinate, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, accountable, consult, and inform

D.

Responsible, accountable, coordinate, and inform

Full Access
Question # 340

A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?

A.

The subject matter experts (SMEs) identified in the stakeholder register

B.

The senior experts with high status in the academic community

C.

The major stakeholders nominated by the project sponsor

D.

The usual review participants holding recognized certifications

Full Access
Question # 341

Which behavior is a management trait?

A.

Asking what and why

B.

Challenging the status quo

C.

Innovating

D.

Relying on control

Full Access
Question # 342

An adaptive team's velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project.

How should the project manager calculate the anticipated velocity for future sprints?

A.

Add a 30% buffer to the velocity to calculate future velocity.

B.

Calculate the average of the past five sprints to predict future velocity.

C.

Change the adaptive tool that the team is using to calculate velocity.

D.

Use the velocity of the last sprint, as it is the most recent one to share.

Full Access
Question # 343

An output of Control Schedule is:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Full Access
Question # 344

Plan Risk Management is the process of defining how to:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Full Access
Go to page: