Summer Certification Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 321

Which of the following investigates the likelihood that each specific risk will occur?

A.

Risk register

B.

Risk audits

C.

Risk urgency assessment

D.

Risk probability and impact assessment

Full Access
Question # 322

Which of these is true of project integration management?

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Full Access
Question # 323

What happens to a stakeholder ' s project influence over time?

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Full Access
Question # 324

The process of prioritizing risks for further analysis or action is known as:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

Full Access
Question # 325

A project manager is performing the procurement management process with three vendors The project team is reviewing the requests for proposal (RFPs).

What type of procurement document is the RFP?

A.

Bid document

B.

Statement of work (SOW)

C.

Source selection criteria

D.

Independent cost estimate

Full Access
Question # 326

What is the purpose of an adaptive standup meeting?

A.

To review what work has been completed, remove impediments, and calculate velocity

B.

To ask the team what work has been completed, calculate velocity, and determine what work will be completed

C.

To ask the team what work has been completed, ask what work will be completed, and report impediments

D.

To update the burndown chart, calculate velocity, and report impediments

Full Access
Question # 327

In a project using agile methodology, who may perform the quality control activities?

A.

A group of quality experts at specific times during the project

B.

The project manager only

C.

All team members throughout the project life cycle

D.

Selected stakeholders at specific times during the project

Full Access
Question # 328

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

Cash Flow Statement of the Project Investment Unit: US$ Billion

Period: 0, 1, 2, 3, 4, 5, 6, 7, 8

Cash inflow: 0, 0, 0, 0, 1200, 1200, 1200, 1200

Cash outflow: 0, 700, 800, 500, 700, 700, 700, 700, 700

Net cash flow (NCF): 0, -700, -800, 300, 500, 500, 500, 500, 500

Accumulative total of net cash flow: 0, -700, -1500, -1200, -700, -200, 300, 800, 1300

A.

Static payback period = 3 + |-1200| / 500 = 5.4

B.

Static payback period = 6 + |300| / 500 = 6.6

C.

Static payback period = 5 + |-200| / 500 = 5.4

D.

Static payback period = 4 + |-700| / 500 = 5.4

Full Access
Go to page: