Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 321

What organizational process asset (OPA) might impact a project's outcome?

A.

Processes, polices, and procedures

B.

Legal restrictions

C.

Infrastructure, resource availability. and employee capability

D.

Financial considerations

Full Access
Question # 322

A Scrum team has a product backlog and a sprint backlog. Which of the following is a correct statement related to these artifacts?

A.

The product backlog does not contain a prioritized list of requirements.

B.

The sprint backlog contains items to be completed during the current sprint.

C.

The sprint backlog contains the list of items prioritized by the product owner.

D.

The product backlog is a subset of the sprint backlog.

Full Access
Question # 323

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?

A.

Project plan

B.

Business case

C.

Budget requirement

D.

Project charter

Full Access
Question # 324

What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?

A.

Sensitivity analysis

B.

Simulation

C.

Decision tree analysis

D.

Influence diagram

Full Access
Question # 325

A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?

A.

12

B.

-12

C.

38

D.

1.15

Full Access
Question # 326

In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

A.

Add this risk to the lessons learned register on project completion.

B.

Add the stakeholder to the stakeholder register and add the risk to the risk register.

C.

Make sure proper testing gets completed to minimize the risk highlighted.

D.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.

Full Access
Question # 327

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Full Access
Question # 328

What can the cost management plan establish?

A.

Cost baseline

B.

Cost estimates

C.

Basis of estimates

D.

Control thresholds

Full Access
Go to page: