Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 361

Perform Quantitative Risk Analysis focuses on:

A.

compiling a list of known risks and preparing responses to them.

B.

assessing the probability of occurrence and Impact for every risk in the risk register.

C.

evaluating the contingency and management reserves required for the project.

D.

analyzing numerically the impact of individual risks on the overall project's time and cost objectives.

Full Access
Question # 362

Tailoring considerations for project scope management may include:

A.

requirements management, stability of requirements, development approach, and validation and control.

B.

WBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables.

C.

business needs, product descriptions, project restrictions, and project management plan.

D.

issues defining and controlling what is included in the project, vended deliverables, and quality reports.

Full Access
Question # 363

What is the role of project management in terms of organizational strategy?

A.

Project management aligns initiatives, prioritizes work, and provides resources.

B.

Project management provides the strategic vision (or an organization lo achieve its goals.

C.

Project management enables the achievement of organizational goals and objectives.

D.

Project management harmonizes components and controls interdependencies to realize specific benefits.

Full Access
Question # 364

Which of the following are outputs of the Define Scope process in Project Scope Management?

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project scope statement and project documents updates

D.

Scope baseline and project documents updates

Full Access
Question # 365

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

A.

Internal enterprise environmental factor

B.

Risk register database

C.

External enterprise environmental factor

D.

Organizational process asset

Full Access
Question # 366

Which of the following sets are inputs to the Collect Requirements process?

A.

Project charter and requirements documentation

B.

Project charter and business documents

C.

Project charter and stakeholder requirements

D.

Business documents and requirements traceability matrix

Full Access
Question # 367

Match the influence with its corresponding category of influence.

Full Access
Question # 368

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Full Access