Question # 25

Which statement regarding the purpose of the business case would be the most true?

A.

Once agreed the business case will become the baseline by which the project will be deployed,

B.

It will act as a reference for the project team regarding the specific. processes to be used forproject delivery.

C.

It will determine which stakeholders are most eligible to become members of the steering group,

D.

It will be referred to throughout the project in order to make decisions about the continuing viability of the project.

Full Access
Question # 26

During the consideration of when and how the development of the project management plan should take place, the objectives of carrying out such an exercise can often appear to be uncertain. As a recommendation, the project management plan should be:

A.

assembled when all information is available.

B.

developed iteratively throughout the early stages of the project.

C.

completed in detail before the project is authorised.

D.

free from detailed schedule information.

Full Access
Question # 27

Risk management should be initiated...

A.

when the Project Management Plan is initiated.

B.

at the time the Work Breakdown Structure is developed.

C.

at the start of the project.

D.

once the project concept is understood.

Full Access
Question # 28

Which one of the following best describes a project stakeholder?

A.

A party who is concerned about the project going ahead.

B.

A party with an interest or role in the project or is impacted by the project.

C.

A party who has a vested interest in the outcome of the project.

D.

A party who has a financial stake in the organisation managing the project.

Full Access
Question # 29

Who is best placed in the project to manage sponsor and user expectations?

A.

The senior management team.

B.

The project manager.

C.

The project management office.

D The project team.

Full Access
Question # 30

To develop and establish a proper communication plan within a project, the project manager needsto consider which type of analysis?

A.

Budget.

B.

Stakeholder.

C.

Resource.

D.

Schedule

Full Access
Question # 31

Which of the following are not considered by quality planning?

A.

Contingency budget for remedial work.

B.

Equipment required for quality testing.

C.

Staff qualified to undertake inspections.

D.

Processes to obtain stakeholder approvals.

Full Access
Question # 32

Which of the following statements refers to how scope is managed in a linear project but not an iterative project?

A.

Teams can act on new knowledge to change the scope.

B.

Teams can re-prioritise requirements within the scope.

C.

The scope of work is the starting point for the implementation of change control.

D.

Scope definition is assumed to be fixed for the whole project

Full Access