Question # 17

To be fully effective, the project manager:

A.

must take into consideration the internal and external environments.

B.

need only deal with the internal environment since the sponsor will deal with the external environment.

C.

should manage the external stakeholders and external environment.

D must liaise with regulating bodies to ensure requirements include the latest legislation.

Full Access
Question # 18

A review undertaken to decide whether a project should proceed into its next phase is known as a...

A.

decision gate.

B.

feasibility study.

C.

milestone review.

D.

evaluation review.

Full Access
Question # 19

Which of the following BEST describes a project issue?

A.

An event that may or may not occur

B.

An opportunity that occurs through change control

C.

A problem that the project manager has to deal with on a day-to-day basis

D.

A problem that must be escalated to the appropriate level of management for resolution

Full Access
Question # 20

We have an expert-written solution to this problem!

Who has ultimate responsibility for project risk?

A.

Steering group.

B.

Risk owner.

C.

Project sponsor.

D.

Project manager

Full Access
Question # 21

A review most closely linked to the phases Of the project life cycle could be described as a:

A.

gate review.

B.

learning review.

C.

handover review.

D.

audit review.

Full Access
Question # 22

What is the importance of having a business case?

A.

It allows the sponsor to use the document as a baseline to calculate project slippage.

B.

It provides an overview of the project team performance at each stage of delivery.

C.

It shows how the project manager is performing in delivering the project

D.

It allows the sponsor to decide on project continuously when used at gate review

Full Access
Question # 23

How are outputs best described?

A.

The changed circumstances or behavior that results from their use.

B.

The work packages developed in the W BS for the project.

C.

The realisation of benefits at the end Of the project.

D.

The tangible or intangible products typically delivered by a project.

Full Access
Question # 24

Which of the following descriptions particularly identifies a risk?

A.

An unplanned delay to the project.

B.

A. current problem that will result in the project going over budget.

C.

An uncertain event that if it occurs will have an effect on one or more of the project objectives,

D.

A. current problem that will result in the project being delayed.