Searching for workable clues to ace the PMI PMI-RMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMI-RMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 33

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X ' s project manager avoid this situation in the future?

A.

Prepare a contingency response plan to implement when delays occur

B.

Ask the other project manager to officially confirm the new date in writing

C.

Request that the other project manager be added to relevant reports

D.

Request that the other project manager inform if any additional delays are expected

Full Access
Question # 34

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

A.

Compatibility

B.

Urgency

C.

Usability

D.

Proximity

E.

Detectability 

Full Access
Question # 35

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Full Access
Question # 36

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

A.

US$68,000

B.

US$52,000

C.

US$120,000

D.

US$80,000

Full Access
Question # 37

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?

A.

Perform time recovery actions.

B.

Execute the prevention plans.

C.

Execute the contingency plans.

D.

Perform change management.

Full Access
Question # 38

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?

A.

Risks are documented to the practicable extent possible.

B.

Probability of the risk was very low. so the risk was not documented.

C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.

D.

A similar risk never occurred in the past, so it was not considered. 

Full Access
Question # 39

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

A.

Earned value management (EVM) variance metrics

B.

A risk burndown chart showing remaining risks

C.

The format established in the risk management plan

D.

An itemized list of remaining risks and their scores 

Full Access
Question # 40

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

A.

Executed the risk strategy response and recorded it in the risk register.

B.

Performed an analysis to affirm the request is valid before submitting.

C.

Informed the client and the project sponsor that the request is being submitted.

D.

Contacted the other stakeholders so they know the request is in process.

Full Access