Summer Certification Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMI-RMP Exam Dumps - PMI Risk Management Professional (PMI-RMP) Exam

Searching for workable clues to ace the PMI PMI-RMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMI-RMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 81

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

A.

Risk description risk response, and quantitative data

B.

Project plan, risk complexity, and secondary risk

C.

Project plan, risk priority, and tool availability

D.

Risk description, risk probability, and risk impact 

Full Access
Question # 82

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project ' s budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

A.

Stakeholder management and communication tools

B.

Team performance reports and analysis tools

C.

Schedule management tools (i.e., Gantt Charts)

D.

Estimation and probability analysis tools (i.e. Monte Carlo simul-ations) 

Full Access
Question # 83

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

A.

Implement the risk response strategies into the risk plan.

B.

Inform the sponsor that these risks should be added according to experience.

C.

Add the risks to the risk register and determine a contingency.

D.

Discuss and evaluate the identified risks with the project team.

Full Access
Question # 84

A Scrum team has recently lost its product owner to another team. A new product owner has been hired for the Scrum team. This product owner is currently new to the project, unfamiliar with the team ' s practices, and does not have a full grasp of the product users. After a few sprints, the product owner is receiving constructive feedback from both internal and external stakeholders related to the direction of the product and its current challenges.

What can the product owner do to improve the product ' s perception among stakeholders and ensure the team understands the product vision? (Choose 2)

A.

Re-assess the product goal, place it on the product backlog, and explain it to the team.

B.

Invite more stakeholders to the daily scrum meetings to voice their opinion of the product.

C.

Create sprint goals and communicate them at the sprint planning event.

D.

Invite product teams to more frequent reviews to observe the team ' s work and encourage feedback.

E.

Invite stakeholders to the sprint retrospective to brainstorm with the team improvements.

Full Access
Question # 85

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project ' s technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?

A.

Immediately hire as soon as the project begins to fall behind schedule.

B.

Hire as soon as the project metrics trigger a risk response.

C.

Only hire when it is economically feasible to do so.

D.

Only hire if risk response is escalated and approved by the stakeholders. 

Full Access
Question # 86

A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

A.

US$20.000 loss

B.

US$20,000 profit

C.

US$40,000 loss

D.

US$100,000 profit

Full Access
Go to page: