Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMI-RMP Exam Dumps - PMI Risk Management Professional (PMI-RMP) Exam

Searching for workable clues to ace the PMI PMI-RMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMI-RMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 41

A newly appointed risk manager for a critical project is working with a project team to develop a risk management strategy. One team member suggested creating an influence diagram to help analyze the options, risks, outcomes, and their relationships. Another team member feels the influence diagram is not enough because this project is important and complex.

Which approach should the risk manager take to improve the quality of the project risk analysis?

A.

Use brainstorming to identify more possible risks.

B.

Use a Monte Carlo simulation to identify risks.

C.

Use a work breakdown structure (WBS) to help analyze risks.

D.

Use a qualitative or quantitative analysis to analyze identified risks.

Full Access
Question # 42

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

A.

Perform a qualitative risk analysis and update the results.

B.

Update the assumptions/exclusions register with the new information.

C.

Update the risk register and prepare for the Monte Carlo analysis.

D.

Perform a quantitative risk analysis and update the results.

Full Access
Question # 43

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Full Access
Question # 44

A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.

What type of risk is being referred to here?

A.

Major risk

B.

Residual risk

C.

Secondary risk

D.

Environment risk

Full Access
Question # 45

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

A.

Provided regular training to the risk owners for plan implementation

B.

Determined risk triggers and thresholds in the risk response plan

C.

Increased communications to influence stakeholder risk responses

D.

Updated the project schedule, adding risk owner implementation tasks.

Full Access
Question # 46

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

A.

Risk mitigation

B.

Risk transfer

C.

Risk acceptance

D.

Risk avoidance

Full Access
Question # 47

A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project.

How should the risk manager address this concern?

A.

Develop a risk breakdown structure {RBS) to identify possible risks.

B.

Develop a risk impact analysis to assess the consequences of possible risks

C.

Develop a probability and impact matrix to analyze possible risks.

D.

Create a risk register to capture and track possible risks. 

Full Access
Question # 48

A project team has just initiated a large project to move an organization ' s headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

B.

The ideal solution is to find alternate documents that provide good visibility on the environment.

C.

The risk identification process can be carried out as long as the project statement is available.

D.

Risk evaluation will be challenging without these elements as a frame of reference.

Full Access
Go to page: