Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMI-RMP Exam Dumps - PMI Risk Management Professional (PMI-RMP) Exam

Searching for workable clues to ace the PMI PMI-RMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMI-RMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 73

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.

Advise the client that the project has exhausted contingency.

C.

Quantify the risk exposure that exceeds project contingency.

D.

Generate reports to assess and communicate the project risk level.

Full Access
Question # 74

A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.

What should the risk manager do?

A.

Study the change logs to implement the approved change requests.

B.

Close out the expired risk and update the relevant project documents.

C.

Get permission from stakeholders before documenting lessons learned.

D.

Continue monitoring the critical response plan on the delivered product.

Full Access
Question # 75

A key hardware component failed during a large software implementation project, with significant organizational impact. The risk owner was on vacation and no one responded to this incident, thereby causing project delays.

What should have been done to prevent this situation?

A.

The project manager should have requested and mandated that no vacations be taken during critical implementation activities or until all implementation had been completed for the project.

B.

The risk manager should have anticipated this situation and planned for schedule buffers in the project schedule to accommodate the likelihood of failed hardware.

C.

The risk owner should have communicated with the project manager so that a designated stakeholder could have been assigned to accept accountability for implementing risk responses.

D.

The risk manager should have taken the responsibility of responding to this risk instead of relying on and waiting for the risk owner to return from vacation.

Full Access
Question # 76

A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project ' s total duration.

After analyzing the quantitative analysis results, which activity should the team pay more attention to?

Use the chart for the analysis.

A.

Activity 3.2

B.

Activity 2.3

C.

Activity 3.5

D.

Activity 1.2

Full Access
Question # 77

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

A.

Suspend the project as the secondary risk will negatively impact residents ' health which is not acceptable.

B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

C.

Assess and record associated secondary risks and proceed to treat them as any other risks.

D.

Proceed with the project as normal since a minor number of residents will be effected negatively.

Full Access
Question # 78

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

A.

Document the concern over the potential excessive additional cost.

B.

Manage the potential excessive additional cost as a new risk.

C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project. 

Full Access
Question # 79

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

A.

Ensure that all project stakeholders have a copy of and understand the project ' s risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 

Full Access
Question # 80

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?

A.

Prioritize opportunities as they are likely to bring benefits to the project.

B.

Analyze the risks and add them to the risk register to continue the process.

C.

Create a separate project to exclusively manage positive risks and threats.

D.

Assign separate stakeholder groups for positive risks and negative risks.

Full Access
Go to page: