Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-RMP Exam Dumps - PMI Risk Management Professional (PMI-RMP) Exam

Go to page:
Question # 9

The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client

Full Access
Question # 10

In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?

A.

Probabilistic and quantitative risk analyses to get the overall risk score

B.

Quantitative risk analysis to get the overall risk score

C.

Probabilistic risk analysis to get the overall risk score

D.

Qualitative risk analysis to get the overall risk score

 

Full Access
Question # 11

A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?

A.

Sensitivity analysis

B.

Qualitative analysis

C.

Statistical analysis

D.

Impact analysis

 

Full Access
Question # 12

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

A.

Perform a qualitative risk analysis and update the results.

B.

Update the assumptions/exclusions register with the new information.

C.

Update the risk register and prepare for the Monte Carlo analysis.

D.

Perform a quantitative risk analysis and update the results.

Full Access
Question # 13

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

A.

Establish a formal and upfront risk identification process.

B.

Use a detailed and quantitative risk assessment process.

C.

Create an effective and clear risk communication process.

D.

Adopt a dynamic and frequent risk management process.

Full Access
Question # 14

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

A.

When the forecast activity date has been met or exceeded

B.

When the stakeholders agree a risk is no longer applicable

C.

When the risk has been realized and can no longer happen again

D.

When iterative data analysis determines the risk is not applicable

Full Access
Question # 15

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

A.

Compatibility

B.

Urgency

C.

Usability

D.

Proximity

E.

Detectability

 

Full Access
Question # 16

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?

A.

Confirm the risk triggers are still valid.

B.

Ask the architect to develop acceptance criteria.

C.

Review the feature with the project team.

D.

Escalate the issue to the project board.

Full Access
Go to page: