Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 281

Which of the following Project Communication Management processes uses performance reports as an input?

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Full Access
Question # 282

Which activity involves ensuring that the composition of a projects configuration items is correct?

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Full Access
Question # 283

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Full Access
Question # 284

One of the tools and techniques of the Manage Project Team process is:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Full Access
Question # 285

Documented identification of a flaw in a project component together with a recommendation is termed a:

A.

corrective action.

B.

preventive action.

C.

non-conformance report,

D.

defect repair.

Full Access
Question # 286

Which of the following is an output of the Distribute Information process?

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Full Access
Question # 287

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Full Access
Question # 288

The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

A.

1.33

B.

2

C.

0.75

D.

0.5

Full Access