Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 113

When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?

A.

Iterative scheduling with backlog

B.

On-demand scheduling

C.

Life cycle scheduling with backlog

D.

Defining Iterative activities

Full Access
Question # 114

Which two processes should be used to influence costs in the early stages of a project?

A.

Estimate Costs and Determine Budget

B.

Plan Cost Management and Estimate Activity Durations

C.

Control Quality and Control Costs

D.

Plan Stakeholder Engagement and Plan Communications Management

Full Access
Question # 115

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

Full Access
Question # 116

In an agile or adaptive environment. when should risk be monitored and prioritized?

A.

Only during the initiation and Closing phases

B.

During the initiation and Planning phases

C.

During each iteration as the project progresses

D.

Throughout the Planning process group and retrospective meeting

Full Access
Question # 117

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

A.

0.88

B.

1.12

C.

0.58

D.

1.58

Full Access
Question # 118

Which of the following describes the similarities of the process groups and project life cycle?

A.

The life cycle involves three project management process groups.

B.

Both provide a basic framework to manage the project.

C.

Each project must have a life cycle and all processes in the five process groups.

D.

The project life cycle is managed by executing the processes within the five process groups.

Full Access
Question # 119

An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?

A.

Informal conversation

B.

Face-to-face meeting

C.

Short email update

D.

Written report

Full Access
Question # 120

Which are inputs for the Plan Quality Management process?

A.

Quality metrics, project documents, and financial performance

B.

Quality management plan, project documents, and quality metrics

C.

Project management plan, project documents, and organizational process assets

D.

Project management plan, quality metrics. and project documents

Full Access
Go to page: