Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 129

Recently, the government published a new tax law giving companies one year to implement the changes. A project was initiated to change the accounting system. Which delivery approach is most suitable in this context?

A.

Predictive, because of the high risk that the company can be fined.

B.

Predictive, because the requirements are clearly defined up-front.

C.

Adaptive, because the government will provide constant feedback.

D.

Adaptive, because the changes have never been implemented before.

Full Access
Question # 130

If a project manager effectively manages project knowledge, a key benefits is that:

A.

all stakeholders have access to the same information.

B.

the project team is able to understand the project status.

C.

project stakeholders have a clear picture of the project.

D.

new knowledge is added to organizational process assets.

Full Access
Question # 131

What tool should a project manager use to efficiently manage project resources?

A.

List of project resources

B.

Resource breakdown structure

C.

Resources detailed in the project scope

D.

Resource requirements

Full Access
Question # 132

When can we say that a project is completed?

A.

When the planned time duration is completed

B.

When the project objectives have been reached

C.

When the project manager has left the team

D.

When the project team decides to stop the work on the project

Full Access
Question # 133

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Full Access
Question # 134

A project manager is creating a project charter to provide a direct link between the project and the organization ' s strategic objectives. What must be considered when creating this document?

A.

High-level requirements and the project team

B.

Key stakeholder list and contingency reserve

C.

Detailed milestone schedule and project objectives

D.

Project purpose and high-level project description

Full Access
Question # 135

Which of the following set of items belongs to the communications management plan?

A.

Escalation processes and meeting management

B.

Project schedule and glossary of common terminology

C.

Escalation processes and stakeholder communication requirements

D.

Interactive communication model and information to be communicated

Full Access
Question # 136

A project lead asks the team to create a work breakdown structure (WBS) of the project ' s scope. The team is confused about how far they should break down the scope.

What should the project lead tell the team?

A.

Decompose to the activity or task level.

B.

Decompose until all of the risks are identified.

C.

Decompose to the work package level.

D.

Decompose until a WBS dictionary is obtained.