Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 105

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Full Access
Question # 106

Resource calendars are included in the:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Full Access
Question # 107

One of the objectives of a quality audit is to:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

Full Access
Question # 108

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Full Access
Question # 109

The total of the planned value (PV) is also known as:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Full Access
Question # 110

Risk responses reflect an organization's perceived balance between:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Full Access
Question # 111

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Full Access
Question # 112

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Full Access