Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 89

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Full Access
Question # 90

Which of the following is an input to the Develop Project Charter process?

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Full Access
Question # 91

Which type of dependency is contractually required or inherent in the nature of the work?

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Full Access
Question # 92

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Full Access
Question # 93

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

A.

0.8

B.

0.89

C.

1.13

D.

1.25

Full Access
Question # 94

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Full Access
Question # 95

The process to ensure that appropriate quality standards and operational definitions are used is:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Full Access
Question # 96

The correct equation for schedule variance (SV) is earned value:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Full Access