Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-ACP Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Go to page:
Question # 9

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.

What should the team do?

A.

Estimate only functional requirements that will impact product quality

B.

Add team resources

C.

Refer the issue to the product owner

D.

Break non-functional requirements into those that can be delivered in the given sprint

Full Access
Question # 10

What should the Scrum Master do?

A.

Ask the product owner how upper management's comments can be redirected.

B.

Direct the developer team to ignore the phone calls and emails.

C.

Ask the product owner to enter the requests into the product backlog as high priority.

D.

Personally respond to upper management's phone calls and emails.

Full Access
Question # 11

What should the agile project leader do?

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.

Full Access
Question # 12

How should the agile practitioner address this?

A.

Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.

B.

Add the issue to the Kanban board and assign it to the team member who has made the most progress on resolving it.

C.

Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.

D.

Document all project issues in a common space and ask the team members to decide on task allocation principles.

Full Access
Question # 13

An agile coach has been hired to improve the performance and quality of developed software. The coach performed an analysis of the software and discovered an excessive number of escaped defects, leading to external failures.

How can the agile coach effectively address and correct defects in the software development process while maintaining predictability and keeping workloads within capacity?

A.

Work with the team to create explicit rules such as coding and quality standards and testing policies.

B.

Discipline the team members and institute status meetings with penalties for any future escaped defects.

C.

Hire more generalized specialists because the current team members cannot keep up with the pace.

D.

Apply work in process (WIP) limits so the developers are not pressured to release code that is problematic.

Full Access
Question # 14

What should the product owner have done differently?

A.

Demonstrated only the completed stories and seek stakeholder feedback

B.

Presented the budget situation and review the cost variance

C.

Reviewed the test results to gain confidence from the stakeholders

D.

Presented a demo of all the stories including the work in progress stories

Full Access
Question # 15

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

A.

Help the team to remove impediments that stall project progress.

B.

Work with the development team to adjust the work plan.

C.

Ask the product owner to assign more resources to the project.

D.

Command and control the team to achieve plan goals.

Full Access
Question # 16

The team is derailed by a demand from a senior manager unrelated to the project. How does the agile coach help the team?

A.

By coaching the team to outperform previous velocity

B.

By coaching the team to adhere to expectations set by the scrum master

C.

By encouraging overestimation to increase velocity

D.

By advising the team to remain committed and focused on project goals

Full Access
Go to page: