Searching for workable clues to ace the CompTIA PK0-005 Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PK0-005 PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 89

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Full Access
Question # 90

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Full Access
Question # 91

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders' feedback.

D.

Have the closeout report approved.

Full Access
Question # 92

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Full Access
Question # 93

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Full Access
Question # 94

A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?

A.

RFP

B.

RFQ

C.

RFB

D.

RFI

Full Access
Question # 95

A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

A.

Confidential information

B.

Protected health information

C.

Personally identifiable information

D.

Security clearance

Full Access
Question # 96

Which of the following software programs would be BEST to use lo store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Full Access