Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PK0-005 Exam Dumps - CompTIA Project+ Certification (2025)

Go to page:
Question # 4

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?

A.

Rollback plan

B.

Release plan

C.

Deployment plan

D.

Contingency plan

Full Access
Question # 5

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Full Access
Question # 6

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Select the new critical path.

Option A

Option B

Option C

Full Access
Question # 7

A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).

A.

Company vision

B.

Global environment

C.

Brand value

D.

Mission statement

E.

Portfolio budget

F.

Local legislation

Full Access
Question # 8

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Full Access
Go to page: