Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PK0-005 Exam Dumps - CompTIA Project+ Certification (2025)

Go to page:
Question # 49

A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

A.

Pareto

B.

Run

C.

Control

D.

Histogram

Full Access
Question # 50

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Full Access
Question # 51

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

Full Access
Question # 52

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

A.

Performance

B.

Smoke

C.

Regression

D.

Unit

Full Access
Question # 53

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Full Access
Question # 54

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

Full Access
Question # 55

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Full Access
Question # 56

A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:

A.

the preferred sponsor's communication channel.

B.

the preferred project manager's communication channel.

C.

the preferred reported communication channel.

D.

email communication as the preferred communication channel.

Full Access
Go to page: