Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PK0-005 Exam Dumps - CompTIA Project+ Certification (2025)

Go to page:
Question # 97

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Full Access
Question # 98

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?

A.

CMS

B.

CRM

C.

EDRMS

D.

ERP

Full Access
Question # 99

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Full Access
Question # 100

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

A.

Sprint retrospective

B.

Sprint review

C.

Sprint planning

D.

Daily Scrum

Full Access
Question # 101

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

A.

RFP

B.

WBS

C.

SLA

D.

SOW

Full Access
Question # 102

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Full Access
Question # 103

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Full Access
Question # 104

Which of the following should be considered first when determining the privacy management for project data?

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Full Access
Go to page: