Question # 177

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Full Access
Question # 178

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Full Access
Question # 179

Through whom do project managers accomplish work?

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders

Full Access
Question # 180

The following is a network diagram for a project.

The total float for the project is how many days?

A.

3

B.

5

C.

7

D.

9

Full Access
Question # 181

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

17

Full Access
Question # 182

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Full Access
Question # 183

Which output is the approved version of the time-phased project budget?

A.

Resource calendar

B.

Scope baseline

C.

Trend analysis

D.

Cost baseline

Full Access
Question # 184

Which item is a cost of conformance?

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap