Summer Certification Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 193

The following is a network diagram for a project.

What is the critical path for the project?

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Full Access
Question # 194

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

A.

Defining, sequencing, estimating activity duration, and developing a schedule model are so tightly inked that they are viewed as a single process.

B.

The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge

C.

An iteractive scheduling and on-demand, pull-based scheduling will be required.

D.

To address the full delivery schedule, a range of techniques may be needed and then need to be adapted

Full Access
Question # 195

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Full Access
Question # 196

When does the project team determine which dependencies are discretionary?

A.

Before the Define Activities process

B.

During the Define Activities process

C.

Before the Sequence Activities process

D.

During the Sequence Activities process

Full Access
Question # 197

Which Knowledge Areas include processes from the Closing Process Group?

A.

Project Quality Management and Project Time Management

B.

Project Scope Management and Project Risk Management

C.

Project Stakeholder Management and Project Cost Management

D.

Project Integration Management and Project Procurement Management

Full Access
Question # 198

In the Plan Stakeholder Management process, expert judgment is used to:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.

B.

Ensure comprehensive identification and listing of new stakeholders.

C.

Analyze the information needed to develop the project scope statement.

D.

Decide the level of engagement of the stakeholders at each required stage.

Full Access
Question # 199

Which process is engaged when a project team member makes a change to project budget with project manager ' s approval

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Full Access
Question # 200

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.

Full Access
Go to page: