Question # 201

The chart below is an example of a:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Full Access
Question # 202

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

Full Access
Question # 203

An issue log is an input to which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Full Access
Question # 204

The component of the risk management plan that documents how risk activities will be recorded is called:

A.

tracking

B.

scoping

C.

timing

D.

defining

Full Access
Question # 205

Technical capability, past performance, and intellectual property rights are examples of:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

Full Access
Question # 206

The following is a network diagram for a project.

How many possible paths are identified for this project?

A.

3

B.

4

C.

6

D.

7

Full Access
Question # 207

Which Process Group includes the Manage Stakeholder Engagement process?

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating

Full Access
Question # 208

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming