Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 201

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

Full Access
Question # 202

Which of the following is provided by the critical path method?

A.

Schedule float

B.

Earned value (EV)

C.

Total float

D.

Schedule value

Full Access
Question # 203

In the Plan Procurement Management process, which source selection criteria analyzes if the seller ' s proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

A.

Technical approach

B.

Technical capability

C.

Business size and type

D.

Production capacity and interest

Full Access
Question # 204

Organizational theory is a tool used in which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Full Access
Question # 205

Which schedule network analysis technique modifies the project schedule to account for limited resources?

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

Full Access
Question # 206

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Full Access
Question # 207

Which of the following is an input to the Direct and Manage Project Execution process?

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Full Access
Question # 208

Which of the following is a strategy to deal with positive risks or opportunities?

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Full Access