Searching for workable clues to ace the Scrum PSM-I Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PSM-I PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 73

When should a Sprint Goal be created?

A.

It should have been created in the previous Sprint during Product Backlog refinement.

B.

It must be established before Sprint Planning in order to begin planning.

C.

A Sprint Goal is not mandatory in Scrum.

D.

At any time during the Sprint.

E.

During Sprint Planning.

Full Access
Question # 74

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Development Team’s ability to deliver.

D.

Its Definition of “Done”.

E.

All of the above.

Full Access
Question # 75

(Which of the following activities will a Product Owner engage in during a Sprint?

Choose the best answer.)

A.

Answer questions from the Developers about items in the current Sprint.

B.

Prioritize the Developers’ work on the Sprint Backlog.

C.

Run the Daily Scrum.

D.

Update management on what is being worked on.

Full Access
Question # 76

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Full Access
Question # 77

(The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component, there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?

Choose the best answer.)

A.

Remind the Product Owner that their primary concern is the flow of value reflected in the ordering of the Product Backlog.

B.

Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate Sprint.

C.

Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Developers.

Full Access
Question # 78

Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)

A.

Arranging the Sprint Backlog for the next Sprint.

B.

The value of work currently represented in the Product Backlog.

C.

Team relations

D.

Definition of Done.

E.

How the Scrum Team does its work.

Full Access
Question # 79

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

A.

The Developers after clarifying requirements with the Product Owner

B.

The Scrum Master.

C.

The Product Owner with input from the Developers.

D.

The Developers, alone.

E.

The most senior people in the organization, including architects and subject matter experts.

Full Access
Question # 80

What may be included in the Sprint Backlog? (choose the best answer)

A.

User Stones

B.

Tasks

C.

Use Cases

D.

Tests

E.

Any of the above (or others) which ate a decomposition of the selected Product Backlog items