Searching for workable clues to ace the PRINCE2 PRINCE2-Agile-Foundation Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PRINCE2-Agile-Foundation PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 33

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 34

Which artifact provides a list of user stories?

A.

Project backlog

B.

Project canvas

C.

Product backlog

D.

Release map

Full Access
Question # 35

According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?

A.

Using visualization to display information

B.

Using meeting minutes to share decisions

C.

Using social media to reach more people

D.

Using email to document discussions

Full Access
Question # 36

Why is Lean Startup included in the ‘starting up a project’ process in PRINCE2 Agile?

A.

Because it explains how a small company can grow using traditional technologies

B.

Because it is designed to manage projects, delivering products in timeboxes

C.

Because it enables agile to be used in challenging and uncertain situations

D.

Because running a project and setting up a new business are the same

Full Access
Question # 37

Which statement about the ‘directing a project’ process is CORRECT?

A.

The project board should attend regular project progress meetings

B.

The project board should make decisions based on the Agilometer risks

C.

A project board member should fulfill the product owner role within a delivery team

D.

The project board should increase the stage-level time tolerance

Full Access
Question # 38

Which is the BEST method of communication to gather feedback?

A.

Receiving emailed diagrams to encourage discussion

B.

Conducting online surveys to obtain a range of opinions

C.

Meeting face-to-face to encourage an exchange of views

D.

Discussing over the telephone to gather feedback quickly from stakeholders

Full Access
Question # 39

In which step of the approach to issue management are options to resolve an issue evaluated?

A.

Capture

B.

Implement

C.

Decide

D.

Recommend

Full Access
Question # 40

Which is a responsibility of the product owner?

A.

Monitor progress of the stage

B.

Ensure project-level risks are identified and assessed

C.

Prepare and maintain the project backlog

D.

Prepare and maintain the product backlog

Full Access