Searching for workable clues to ace the PRINCE2 PRINCE2-Agile-Foundation Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PRINCE2-Agile-Foundation PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 17

Which statement about the ‘directing a project’ process is CORRECT?

A.

The project board may pull reports from the information radiator

B.

As a minimum, the project board should receive oral reports from the project manager

C.

The project board should attend the delivery team’s daily stand up meeting

D.

The project board should receive regular reports focusing on cost and time overruns

Full Access
Question # 18

What information is NOT typically displayed on a burn chart?

A.

Effort remaining

B.

Team working agreements

C.

Actual amount of work done

D.

Amount of time elapsed

Full Access
Question # 19

What is the purpose of the ‘agile enablement’ workshop?

A.

To identify, assess, and plan for risks associated with transitioning products into operations

B.

To identify, assess, and plan for risks associated with agile adoption

C.

To identify, assess, and plan for risks associated with project delivery

D.

To identify, assess, and plan for risks associated with business as usual

Full Access
Question # 20

In Scrum, what answers the question ‘what can be done this sprint?’

A.

Daily scrum

B.

Sprint review

C.

Sprint planning

D.

Increment

Full Access
Question # 21

Which well-known agile method uses visualization, and controls work in progress?

A.

Scrum

B.

Lean Startup

C.

Lean

D.

Kanban

Full Access
Question # 22

Which statement about the ‘accept that the customer doesn't need everything’ target is CORRECT?

A.

It is achieved by testing only a few features to deliver on time

B.

It is achieved by ensuring that the operational product has complete documentation

C.

It is based on the concept that people generally use a limited number of product features

D.

It enables a more accurate final product to be produced

Full Access
Question # 23

In which process should the requirements for delivery of specialist products be agreed?

A.

Initiating a project

B.

Managing product delivery

C.

Starting up a project

D.

Managing a stage boundary

Full Access
Question # 24

What is the purpose of the “agile enablement” workshop?

A.

To identify, assess, and plan for risks associated with project delivery

B.

To identify, assess, and plan for risks associated with team delivery

C.

To identify, assess, and plan for risks associated with Agile adoption

D.

To identify, assess, and plan for risks associated with enterprise agility

Full Access