Searching for workable clues to ace the PeopleCert MSP-Practitioner Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s MSP-Practitioner PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 25

Which of the following is NOT normally a characteristic of the Vision Statement?

A.

It must describe a desirable future

B.

It is short

C.

Key benefits are implicit

D.

It must be time dependent

Full Access
Question # 26

Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

Full Access
Question # 27

When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?

A.

Seek further funding for the programme

B.

Design a Blueprint that is less ambitious

C.

Close the Programme

D.

Find a different approach to delivering the Blueprint

Full Access
Question # 28

Which of the following is a critical organizational element?

A.

Leading change

B.

Stakeholder engagement

C.

Quality management and assurance

D.

Delivery mechanisms for change

Full Access
Question # 29

The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.

Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?

A.

Access control

B.

Integrity

C.

Storage

D.

Version control

Full Access
Question # 30

The Smart Meter Programme is in Tranche 2 and the Customer Processes Project is delivering ahead of schedule. This means that fewer resources are required to complete the project. The Training Project, which was due to start in Tranche 3, has now become a higher priority and needs to be started early. The programme manager has recommended starting the Training Project now although Tranche 2 and Tranche 3 will then overlap.

Is this an appropriate application of the structure' theme, and why?

A.

Yes, because available resource capacity should be fully utilized throughout the programme

B.

Yes, because tranches may overlap if the programme is making good progress and capability is available

C.

No, because tranches should be sequential to enable end-of-tranche reviews to take place before the next tranche is approved

D.

No, because tranches should remain sequential if overlapping the tranches would increase the risks to programme delivery

Full Access
Question # 31

The engineering department has been asked to produce a weekly report for the programme board. The report will include data on how many new water meters have been installed in the last seven days. The programme manager is writing the assurance approach. The engineering department report has been included as part of the first line of defence.

Is this an appropriate application of the assurance’ theme, and why?

A.

Yes, because the increased number of gas and electricity customers is dependent on the new water meters being installed

B.

Yes, because the programme board should use the report to monitor the progress of ongoing engineering work

C.

No, because the reporting progress by the engineering department demonstrates application of the ‘decisions' theme

D.

No, because everyone in the programme should have access to progress information, not just the programme board

Full Access
Question # 32

The Employment Contracts Project in Tranche 1 will identify the skills needed by sales staff. However, the Customer Processes Project in Tranche 2 will define new ways to sell gas and electricity to existing water customers which may result in changes to the previously defined skills requirements. If any rework is required, this would delay increasing the number of electricity and gas customers. The programme manager has set up a process to independently monitor the situation, so they can be warned immediately if this becomes likely to happen.

Which principle is being applied MOST by the programme manager when implementing the independent monitoring, and why?

A.

Align with priorities, because the content of Tranche 2 should be changed to reflect any emerging information

B.

Align with priorities, because the business case should be updated as a result of any identified delays to benefits

C.

Realize measurable benefits, because outcomes of benefit should be embedded at intermediate landing points at the end of each tranche

D.

Realize measurable benefits, because assuring risks to the benefits should contribute to improved decision-making

Full Access
Go to page: