Question # 49

You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?

A.

Function points

B.

Extrapolation

C.

Planning poker

D.

Three-point estimation

Full Access
Question # 50

One of your team members is struggling to identify the requirements to be tested for a project The requirements documents are not conventional but you have determined that the data is there. If they do some digging to find it Given this information in what competence area does this person need to improve?

A.

Professional competence

B.

Methodical competence

C.

Social competence

D.

Personal competence

Full Access
Question # 51

It the lest manager must repeatedly step in to resolve conflicts within the team what phase is the team in and what competencies are required from the test manager?

A.

Forming Professional

B.

Storming Social

C.

Norming Personal

D.

Performing Methodological

Full Access
Question # 52

You are managing the testing for a bank card project. The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lot of risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving

You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?

A.

Automate the testing of the untested elements to ensure they are covered

B.

Block the go-live and start testing the low-risk elements immediately

C.

Transfer the risk of the untested low-risk items to the help desk

D.

Select one of the low-risk elements and perform depth testing to assess the residual risk

Full Access
Question # 53

Which of the following best describes the appraisal costs in the cost of quality'

A.

The cost spent preventing defects from occurring in the first place

B.

The cost for performing dynamic testing

C.

The cost for fixing defects

D.

The cost for lawyers to deal with a lawsuit over a defect

Full Access
Question # 54

What occurs In the retrospective closing?

A.

Everyone shakes hands

B.

The data collection methods are reviewed

C.

The strengths and opportunities for improvement in the retrospectives are discussed

D.

A brainstorming session is held to discuss the solutions to the root causes of the most significant issues

Full Access
Question # 55

You have assembled the following cost of quality numbers 200 defects were found prior to release and 100 were found after.

Given this information what is the total cost of quality for this project?

A.

$300,000

B.

$200,000

C.

$100,000

D.

$10 000

Full Access
Question # 56

Your team has been working on an Agile project for two months. There is a retrospective at the endof each sprint One of the data items reviewed is how many defects are being caught by users rather than by testers. The test team is being blamed for these escapes

What do you need to do to make these sessions more productive?

A.

You should attend the retrospective instead of the individual testers

B.

You should do root cause analysis to prove the developers are responsible

C.

You should gather metrics to present to the team regarding all the hours spent testing

D.

You should help the team brainstorm ideas on how to improve the testing to eliminate the escapes