Searching for workable clues to ace the Construction Specifications Institute CDT Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CDT PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 25

In the AIA A201 General Conditions of the Contract for Construction, whom is responsible for property insurance for a project?

A.

Surety, on contractor's behalf.

B.

Owner, unless assigned to contractor.

C.

Owner and contractor, jointly.

D.

Contractor, unless assigned to owner.

Full Access
Question # 26

An architect/engineer wants to schedule monthly meetings with a contractor and owner to discuss matters pertinent to timely and successful completion of the work. Which type of meeting should they schedule?

A.

Workflow meeting

B.

Preinstallation meeting

C.

Progress meeting

D.

Schedule monitoring meeting

Full Access
Question # 27

An electrical engineer completes a set of electrical drawings and specifications for a project, except for the site electrical work which is indicated on the civil drawings. Which of the following is the intent of the contract documents?

A.

The civil contractor is to place the concrete bases and the electrical contractor is to install the site lighting.

B.

The civil contractor is to place the concrete bases and the site lighting, with the electrical contractor making the final connections.

C.

The general contractor needs to coordinate the work and verify that the electrical subcontractor bids the site electrical.

D.

The electrical engineer does not need to control how the work is to be assigned to subcontractors.

Full Access
Question # 28

Under the design-bid-build project delivery, what is the next step after the procurement phase has ended to award the contract for construction?

A.

The contractor begins negotiating agreements with subcontractors.

B.

The owner forwards construction contract agreements to subcontractors.

C.

The contractor and owner issue an amendment indicating the project is in the construction phase.

D.

The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.

Full Access
Question # 29

In what project stage does the architect/engineer obtain and document the owner's decisions about specific products and systems?

A.

Construction documentation

B.

Design

C.

Project conception

D.

Programming

Full Access
Question # 30

What does the Integrated Project Delivery (IPD) process involve?

A.

A collaborative, integrated, and productive team composed of key project participants

B.

Traditional delivery methods and team relationships for improving project performance by understanding the qualifications and attributes of team members

C.

Responsibility silos for greater efficiencies, leading to project success

D.

Segregat knowledge gathered as needed with paper-based communications to team members

Full Access
Question # 31

Which is the reference document that includes guidelines and tools for the organization and presentation of design and construction drawings?

A.

AIA CAD Layer Guidelines

B.

National Institute of Building Sciences

C.

National BIM Standard – United States

D.

U.S. National CAD Standard

Full Access
Question # 32

If the contractor discovers that a part of the contract documents is in violation of the building code, what should the contractor do?

A.

Notify the architect/engineer in writing

B.

Proceed with the work in accordance with the contract documents

C.

Request a variance from the building authority

D.

Stop all work until the issue is resolved

Full Access