Black Friday Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

CDT Exam Dumps - Construction Documents Technologist

Searching for workable clues to ace the Construction Specifications Institute CDT Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CDT PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 9

What could a reference standard specification be based upon?

A.

Project manual for similar project

B.

Design intent

C.

Trade association standard

D.

Manufacturer's specification section

Full Access
Question # 10

Which team member is actively involved and interested in all phases of the project?

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Full Access
Question # 11

During the schematic design phase, a contingency line item in the estimate would be included to cover which of the following?

A.

Allowances

B.

Unit prices

C.

Unknown factors

D.

Alternates

Full Access
Question # 12

Which of the following is a scaled view?

A.

Perspective

B.

Foundation plan

C.

Riser diagram

D.

Isometric

Full Access
Question # 13

With whom does the responsibility for maintaining record documents at the project site rest?

A.

Contractor

B.

Architect/engineer (A/E)'s consultant

C.

A/E's project representative

D.

Owner's project representative

Full Access
Question # 14

Lump sum, unit price, and cost-plus-fee are examples of what?

A.

Delivery method

B.

Bonding system

C.

Basis of payment

D.

Cost estimate

Full Access
Question # 15

Modifications to the contract documents after execution of the owner–contractor agreement include which of the following?

A.

Change order, construction change directive, and field order

B.

Field order, construction change directive, and request for information

C.

Addendum, change order, and request for information

D.

Supplemental instructions, work change directive, and addendum

Full Access
Question # 16

During the project closeout phase, what is an appropriate task for the facility manager?

A.

To ensure they have received the required spare parts, extra stock materials, and any necessary training needed in order to maintain the facility in the first year

B.

To coordinate with the architect a final clean-up and site restoration

C.

To hire a new security company to ensure maintenance and ground management

D.

To draft the final changes on the as-built documents

Full Access
Go to page: