Question # 17

In quantitative POF analysis, when failure data for each piece of equipment is unavailable, general industry failure data can be used by what means?

A.

Using engineering judgment to estimate the POF categories

B.

Adjusting the data by qualified persons to make it more equipment specific

C.

Multiplying it by numerical fractions obtained from applicable industry literature

D.

Categorizing the probability of failure as high, medium or low with different orders of magnitude

Full Access
Question # 18

An iso-risk line on a risk plot is a line:

A.

of constant risk.

B.

of same-risk consequence.

C.

showing direction of increasing risk.

D.

of same-risk probability.

Full Access
Question # 19

A likely trigger for an RBI reassessment would be after:

A.

API RP 580 Risk-Based Inspection has been updated.

B.

a mitigation strategy has been implemented.

C.

RBI team members have changed.

D.

a sensitivity analysis on the risk determination has been conducted.

Full Access
Question # 20

Which of the following is a tool used to show the effectiveness in depicting a combination of events that could result in a loss of containment event?

A.

Physical model

B.

Dual-mode model

C.

Logic model

D.

LOC model

Full Access
Question # 21

Once a credible damage mechanism(s) has been identified, the associated failure mode should also be identified. An example of a failure mode is:

A.

pit-to-leak

B.

localized thinning

C.

chloride cracking

D.

weld undercut

Full Access
Question # 22

Once organizing the work process for RBI program planning has been completed, the next step is the identification of the:

A.

appropriate mitigation activities that will be considered.

B.

credible damage mechanisms and failure modes.

C.

applicable design and inspection codes and standards.

D.

data and information required to be collected for RBI analysis.

Full Access
Question # 23

A most common indicator in consequence analysis is:

A.

cost of loss.

B.

environmental damage.

C.

affected area.

D.

number of injuries.

Full Access
Question # 24

Which of the following statements is correct with regard to the potential reduction of inspection cost by using RBI?

A.

Equipment integrity is the focus.

B.

RBI will eliminate many internal inspections.

C.

On-stream inspections are as effective as internal inspections.

D.

RBI will probably raise the total cost of inspection for a given unit.

Full Access