Searching for workable clues to ace the BCS TM3 Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s TM3 PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 9

Which of the following is a generic good practice in adopting and rolling out of a new test tool?

A.

Define guidelines for the use of the tool

B.

Identify opportunities for process improvement supported by the tool

C.

Understand how the tool can technically and organisationally be integrated into the software development lifecycle

D.

Consider the pros and cons of the various licensing models

Full Access
Question # 10

Which of the following is not something you should do when performing a Belbin assessment with an Agile team?

A.

Team members use a self-assessment questionnaire to identify their own strengths and weaknesses in relation to nine Belbin roles.

B.

Feedback is provided to the individual team members by another team member using the observer assessment questionnaire.

C.

The team member roles should be balanced with the Belbin team roles model to identify any missing or overrepresented roles and adjust accordingly.

D.

The team should not align the team's roles with the team's goals and expectations. These should be kept independent.

Full Access
Question # 11

You are a tester working in an Agile team in the finance domain. The team consists of 6 members, and you are the only tester. The team is responsible for the development and maintenance of a mobile front-end application. The application is considered to be critical with respect to customer impact and market branding.

You have been asked to identify which test management activity needs to be performed within the team to enhance test maturity and achieve a higher level of product quality.

Which test management activity would you recommend the team should adopt?

A.

Define quality criteria for user stories and acceptance criteria

B.

Provide detailed estimations early for each test level

C.

Perform product risk identification and analysis

D.

Increase coverage by automating more tests

Full Access
Question # 12

Assume that you are using traceability to manage test case coverage against test conditions. During test analysis, three test conditions were identified. Test design for system testing has been completed and 10 test cases (TC1 to TC10) have been designed, as described by the following traceability matrix (“C” indicates a critical test case, while “NC” indicates a non-critical test case):

[traceability matrix not visible in the prompt]

The exit criterion for system testing states that each test condition must have all the associated critical test cases successfully executed (passed) AND all associated non-critical test cases at least executed.

The following is the situation after three days of system testing:

TC1, TC2, TC4, TC5, TC7, TC9: passed

TC3, TC10: failed (with an associated open defect report)

TC6, TC8: not run

Management wants to decide whether to release the system. You advise them that the system does not yet meet the defined exit criteria.

Based only on the given information, which test condition does not yet meet the stated exit criterion?

A.

Test condition 1

B.

Test condition 2

C.

Test condition 3

D.

None, all meet the stated exit criteria

Full Access
Question # 13

You are a process improver and have decided to use the data from the defect management system to identify and drive improvement actions… Which of the following options could have been identified as missing from the defect reports to be used for process improvement?

A.

Steps to reproduce the failure, along with the actual and expected results

B.

The priority to fix the problem

C.

The status of the defect

D.

The software lifecycle phase in which the defect was detected

Full Access
Question # 14

Which status would typically be assigned to a false-positive defect report during defect management?

A.

Rejected

B.

Accepted

C.

Resolved

D.

Deferred

Full Access
Question # 15

Ability to act with confidence is an important skill for a person to perform successfully in a project or team.

To which area of competence does "ability to act with confidence" belong?

A.

Professional competence

B.

Methodological competence

C.

Social competence

D.

Personal competence

Full Access