Question # 4

Why is a confidence vote held at the end of program increment (Pl) planning?

A.

To build shared commitment to the plan

B.

To remove the risks for the Pl

C.

To ensure the business owners accept the plan

D.

To hold the teams accountable if the Agile release train (ART) does not deliver on its commitment

Full Access
Question # 5

What is ultimately intended to be supported by the use of a Program board?

A.

Problem solving

B.

Program predictability

C.

Feature delivery

D.

Dependency review

Full Access
Question # 6

Teams are reporting a high level of success through their individual quantitative meas-urements, but the system results say otherwise. What should the Release Train Engineer do to help the teams deliver more value?

A.

Coach the Scrum Masters on good retrospective techniques and ensure teams are defining and taking a systems view approach to improvements

B.

Share the quantitative measurement results with Product Management and lead-ership and ask for their input

C.

Diagnose the differences between the measurements and the results and suggest improvement items to each team

D.

Work with the team that is struggling the most to discover patterns that can be ap-plied to the other teams

Full Access
Question # 7

What promotes alignment between the business owners and product management?

A.

Quantification of transaction and holding costs

B.

Epics supported by Lean Business Cases

C.

Prioritized Program Backlog

D.

Applying cadence and synchronization

Full Access
Question # 8

Why would a Release Train Engineer use an Iteration and Program Increment Calendar?

A.

To know the cycle time between important team and train events

B.

To ensure that key ceremonies don't conflict with non-SAFe ceremonies

C.

To create a BVIR of the important team and ART milestones

D.

To visualize the Agile Release Train's cadence and synchronization

Full Access
Question # 9

Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)

A.

Risks on the teams' planning boards are resolved by the Release Train Engineer

B.

Teams use color-coding for their backlog items as a reminder that they are re-quired to have all backlog item types on their planning boards

C.

Draft objectives and uncommitted objectives are written

D.

All teams' planning boards are visible and use the same color-coding

E.

Draft objectives are written but do not include exploration Enablers

Full Access
Question # 10

Product Management is responsible for which activity?

A.

Establishing an architectural vision for the Agile Release Release Train

B.

Defining Program Backlog content

C.

Prioritizing the Portfolio Backlog

Full Access
Question # 11

While facilitating Program Increment (PI) Planning readiness activities, the Release Train Engineer (RTE) notices a Feature that is risky to the teams because the technology is new. Which of the following could reduce the risk?

A.

Ensure engineering managers are directing the development process

B.

Coach the teams to create exploration Enablers

C.

Ask for a presentation of a detailed design before the PI Planning meeting

D.

Make sure all the technical specifications are written before PI execution

Full Access
Question # 12

Which two behaviors should a Scrum Master represent as a coach? (Choose two.)

A.

Provide subject matter expertise

B.

Lay out the team's plan for the iteration

C.

Encourage the team to learn from their mistakes

D.

Set long-term goals for the team

E.

Focus on deadlines and technical options

Full Access
Question # 13

When planning for a distributed Program Increment (PI) Planning event with a large dif-ference in time zones, what are two key preparation and facilitation focus areas for a Re-lease Train Engineer (RTE)? (Choose two.)

A.

Share the outcomes of preparation meetings with local Scrum Masters so they can arrange local rooms

B.

Have a single RTE and technical support person that acts as a central point of communication for all locations

C.

Adjust the PI agenda to 2.5 – 3 days, allowing for overlapping hours

D.

Split up the PI Planning event per time zone and then have the final plan review, confidence vote, and planning retrospective as one centralized meeting

E.

Arrange and test presentation audio and video connectivity in all locations

Full Access
Question # 14

What are two ways program risks can be categorized? (Choose two.)

A.

Identified

B.

Explained

C.

Deferred

D.

Resolved

E.

Owned

Full Access
Question # 15

What is a benefit of capacity allocation?

A.

It enables more effective time tracking

B.

It ensures all value streams in the portfolio are appropriately funded

C.

It ensures different types of backlog items are not compared against one another

Full Access
Question # 16

Which statement is true about nonfunctional requirements?

A.

They stay in the Portfolio Backlog until implementation capacity is available

B.

They are split into Features and acceptance criteria is established

C.

They operate as constraints on the design of the system

Full Access
Question # 17

Which statement is true about estimating Features using Story points?

A.

More than one team may be involved in the estimation

B.

T-shirt sizing is the best way to estimate features

C.

Feature estimation is performed solely by Product Managers

Full Access
Question # 18

Enabler Epics are used to advance what in order to support upcoming Business Epics?

A.

Value Stream(s)

B.

The Continuous Delivery Pipeline

C.

The Architectural Runway

Full Access
Question # 19

Which three topics are covered on the first day of the Program Increment (PI) Planning event? (Choose three.)

A.

Ishikawa diagrams

B.

Team velocity Metrics

C.

Business context

D.

Cumulative flow diagrams

E.

Product/Solution Vision

F.

Architecture Vision and development practices

Full Access
Question # 20

What can occur as a result of not having an Innovation and Planning Iteration?

A.

Delivery can be stifled incrementally

B.

Bottlenecks can be hard to identify and resolve

C.

Technical debt can grow uncontrollably

D.

Teams can have no time for fixing bugs

Full Access
Question # 21

What is the name of the event where all team members determine how much of the team's backlog they can commit to delivering during an upcoming Iteration?

A.

Backlog refinement

B.

Solution planning

C.

lteration planning

D.

Solution Demo

Full Access
Question # 22

The business must depend on the team for what in order to do any meaningful planning?

A.

Team capabilities

B.

Commitment to the plan

C.

Measurements

D.

A cross-functional skill set

Full Access
Question # 23

Which of the following is true of Iteration Goals in SAFe?

A.

They provide KPIs for tracking progress and value realization

B.

They enable teams to keep aligned with PI objectives

C.

They describe the value of planned Features and Enablers

D.

They provide quantifiable metrics to be used in retrospectives

Full Access
Question # 24

When estimating stories, what is the Scrum Master's key responsibility?

A.

Ensure the team gives accurate estimates

B.

Ensure everyone on the team participates

C.

Provide information about customer needs

D.

Limit discussion to manage timeboxes

Full Access
Question # 25

During Program Increment (PI) Planning, a scrum of scrums occurs just before the draft plan review. The Scrum Master from one team raises an issue that one of the Product Managers just showed up to the planning area with a priority wish list of items. These items do not align with the Feature prioritization. What is the most likely planning anti-pattern causing this sudden impediment?

A.

There is strong alignment between business and marketing

B.

Planning decisions have been centralized

C.

Prioritization by Product Management was performed autonomously not collaboratively

D.

There is no social network that Solution development relies on

Full Access
Question # 26

Which core competency describes the ability to deliver continuous value?

A.

Organizational Agility

B.

Lean Portfolio Management

C.

Business Agility

D.

Agile Product Delivery

Full Access
Question # 27

How does SAFe handle the 'fear of conflict' team dysfunction?

A.

Reviews results at the end of every iteration

B.

Avoids discussion of disagreements

C.

Has teams engage in retrospectives

D.

Uses scrum to create a safe environment for conflict