Searching for workable clues to ace the Scaled Agile SAFe-RTE Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s SAFe-RTE PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 49

Which role should the Release Train Engineer play related to a hackathon event?

A.

Ensure the teams have allocated story points in the Innovation and Planning Itera-tion during the Program Increment to account for the effort

B.

Get approval for work to be done in the hackathon

C.

Allow the teams as much flexibility as possible to promote innovation

D.

Work with development leaders to make sure they give clear and detailed guid-ance to the developers on what is expected

Full Access
Question # 50

Which statement is true about the definition of done (DoD)?

A.

The DoD is not used by the teams because it is used as a method to manage tech-nical debt across the ART

B.

At the higher levels there is only one DoD for everything that passes through the Agile Release Train to a Solution increment or a release

C.

The teams share one common DoD

D.

The DoD should evolve as system capabilities evolve

Full Access
Question # 51

Which statement is true about nonfunctional requirements?

A.

They stay in the Portfolio Backlog until implementation capacity is available

B.

They are split into Features and acceptance criteria is established

C.

They operate as constraints on the design of the system

Full Access
Question # 52

Which statement is true about using a Program Kanban system

A.

All work is visualized, progress is continually tracked

B.

WIP limits are used to provide any needed buffers

C.

Work is pushed through the Kanban to ensure train capacity is utilized

D.

The board tracks features, dependencies and milestones

Full Access
Question # 53

What is the primary purpose of PO sync?

A.

To build objectives for the Program Increment

B.

To assess progress of the Program Increment and adjust scope and priority as needed

C.

To align with the scrum of scrums participants on the status of the Program Increment

Full Access
Question # 54

An Agile Release Train (ART) is frequently discovering compatibility issues between the developed Solution and the Enterprise information architecture. What can the Release Train Engineer do to prevent this from occurring?

A.

Develop more detailed Feature definitions

B.

Add data Architects onto the ART

C.

Confirm attendance of architectural representatives at Program Increment (PI) Planning

D.

Conduct the entire data architecture design upfront

Full Access
Question # 55

Why is a confidence vote held at the end of program increment (Pl) planning?

A.

To build shared commitment to the plan

B.

To remove the risks for the Pl

C.

To ensure the business owners accept the plan

D.

To hold the teams accountable if the Agile release train (ART) does not deliver on its commitment

Full Access
Question # 56

Which statement is true about estimating Features using Story points?

A.

More than one team may be involved in the estimation

B.

T-shirt sizing is the best way to estimate features

C.

Feature estimation is performed solely by Product Managers

Full Access