Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PSP Exam Dumps - Planning & Scheduling Professional (PSP) Exam

Searching for workable clues to ace the AACE International PSP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PSP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 33

You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor has included codes for each activity that identify {1) the category of work and (2) the trade/subcontract performing the work. What can this code information be used for?

A.

Group schedule activities together based on their start dates

B.

Display detailed information regarding the sequencing of activities in the schedule

C.

Organize reports to group related work activities

D.

Display resources me contractor plans to use on each activity

Full Access
Question # 34

If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?

A.

Proceed with company processes even if they conflict with the client

B.

The client contract specifications always have priority

C.

Review any differences and negotiate workable specifications

D.

Suggest that the client issue a change order, accepting the contractor's processes

Full Access
Question # 35

The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.

A.

Estimate at completion (EAC)

B.

Budget at completion (BAC)

C.

Budgeted cost of work performed (BCWP)

D.

Budgeted cost of work scheduled (BCWS)

Full Access
Question # 36

Budgeted cost of work scheduled is _______________________.

A.

The value of the completed work expressed in terms of the budget assigned to that work

B.

The total authorized budget for accomplishing the project scope

C.

The expected total cost of an activity, group of activities or the project

D.

The sum of all budgets for work scheduled to be accomplished within a given time period

Full Access
Question # 37

Value engineering is:

A.

targeted at the design itself

B.

intended to provide the least life-cycle cost

C.

established to provide the greatest value

D.

intended to determine if the project will be completed economically

Full Access
Question # 38

At the end of month one, did the delay to the parking structure foundation delay the project?

A.

NO.

B.

Yes, by 4 calendar days.

C.

Yes, by 14 calendar days.

D.

Yes, by 9 calendar days.

Full Access
Question # 39

The Work Breakdown Structure (WBS) is established to reflect the:

A.

lowest level of the project estimate

B.

lowest level reporting back to the program WBS

C.

lowest level of effort scope

D.

lowest level where the work is managed

Full Access
Question # 40

Which of the following is not an internal stakeholder?

A.

Owner

B.

installer

C.

Subcontractor

D.

Prime Contractor

Full Access
Go to page: