Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PSP Exam Dumps - Planning & Scheduling Professional (PSP) Exam

Searching for workable clues to ace the AACE International PSP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PSP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 17

What project cost elements would NOT normally be reflected in the Activity 1000?

A.

Home office expenses

B.

CPM processing and updating

C.

Materials used in the construction

D.

Job site quality control

Full Access
Question # 18

What portion of Activity B is on the critical path?

A.

Last half of the activity

B.

None of it

C.

First half of the activity

D.

The whole activity

Full Access
Question # 19

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

A.

407 days

B.

362 days

C.

255 days

D.

267 days

Full Access
Question # 20

The Cost Estimate is NOT developed to:

A.

quantify cost, and price the resources required by the Scope of Work

B.

predict uncertain future costs

C.

providing the basis for budgets

D.

determine the project performance goals

Full Access
Question # 21

When should the project documents be reviewed to assess their impact on the organization and administration of a project?

A.

After the Award and before the NTP

B.

During the Bid Phase

C.

Before the commercial decision to Did on the project

D.

After the NTP

Full Access
Question # 22

Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

A.

407 days

B.

255 days

C.

267 days

D.

477 days

Full Access
Question # 23

Due to the delayed completion of Product Testing, the Release for Manufacture milestone was delayed by 5 workdays which thus delayed starting the Draft Product Manual activity. If the Print Product Manual activity is also delayed by 10 workdays, what is the delay to completing the Product Available milestone?

A.

15 days

B.

0 days

C.

10 days

D.

5 days

Full Access
Question # 24

Determine the correct formula and date for the late finish for Activity 9004.

A.

LF of 10002 less 24 days

B.

LS of 9004 plus 72 days

C.

LF of 8001 plus 72 days

D.

LS of 10002 less lag of 7 days plus 1 day equaling 20 Nov 2023

Full Access
Go to page: