Labour Day Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMI-200 Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Question # 4

What do project reports show during the Sprint review meeting?

A.

Estimates compared to the baseline

B.

Actual results to the plan

C.

Return on investment (ROI)

D.

Earned value measurement (EVM)

Full Access
Question # 5

For a critical project, a new team has been formed from various departments. The project manager should start team building by:

A.

Creating a project charter, documenting roles and responsibilities of each member, and sending it to the team members.

B.

Taking the team offsite for icebreaker sessions and other activities to ensure team members get to know each other.

C.

Assembling the team and discussing roles and responsibilities of each member on the team.

D.

Assembling the team and asking the members to achieve a milestone in a small iteration.

Full Access
Question # 6

An Agile team best ensures product quality through:

A.

The development team’s use of pair programming.

B.

Quality assurance’s daily collaboration with the development team.

C.

More frequent inspection after each iteration.

D.

Feedback gathered during iteration retrospectives.

Full Access
Question # 7

A common reason that a story may not be estimable is that the:

A.

team lacks domain knowledge.

B.

business needs are prioritized over the system design.

C.

developers do not understand the tasks related to the story.

D.

team has no experience in estimating.

Full Access
Question # 8

The three questions asked at every Daily Scrum should be: “What have you accomplished since the last Daily Scrum?”;”What are you planning to accomplish between now and the next Daily Scrum?”; and:

A.

What is preventing you from completing your work effectively?

B.

What is yourcurrent performance velocity?

C.

Are you on track to complete assigned story points?

D.

How many story pointswill you complete this sprint?

Full Access
Question # 9

A full cycle of design-code-verifyrelease practiced by extreme Programming (XP) teams is called:

A.

Story

B.

Timebox

C.

Iteration

D.

Burndown

Full Access
Question # 10

How is the participatory design process characterized?

A.

A well-planned and well-documented process is documented for each of the iterations in the project.

B.

Users including project team members participate in the planning process for the project plan.

C.

End users participate and assist in the design process from the beginning of the project.

D.

A high level brainstorming process is conducted for the project team and the project sponsor.

Full Access
Question # 11

In Agile projects, how are planning outputs shared with stakeholders?

A.

Using the most highly visible method possible

B.

On a need-to-know basis depending on role

C.

According to the project communications plan

D.

Through a series of stakeholder meetings

Full Access
Question # 12

Applying the Pareto rule when prioritizing the Product Backlog means that:

A.

features that are lower priority are more likely to slip to the next iteration.

B.

the value of a feature is not realized until the feature is complete.

C.

more recent requests are usually more important to the business.

D.

a small percentage of the work will provide a large percentage of the value.

Full Access
Question # 13

What is the first thing that a team should do to estimate user stories for a project?

A.

Sort the user stories according to priority.

B.

Schedule a team meeting to understand them.

C.

Define the story points measure.

D.

Estimate through function point analysis.

Full Access
Question # 14

When interacting with team members, the Agile project manager should:

A.

Ask team members to do things by phrasing the statement as a request rather than as a demand.

B.

Ignore team member input and emotions when important decisions have to be made.

C.

Proceed cautiously when requesting team members to do something likely to make them unhappy.

D.

Disagree with the team based on the merit of the issue without considering how the team is feeling.

Full Access
Question # 15

Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?

A.

Split the stories into smaller ones to allow the customer to choose the pieces that they want.

B.

Have the team provide guidance into where their priorities lie to the customer.

C.

Provide additional technical details to give the customer insight into technical challenges.

D.

Have the team rewrite the stories with additional details to clarify requirements.

Full Access
Question # 16

After three iterations, the problems impeding an Agile team appear to be similar in nature to problems faced in earlier iterations. Inspection of the retrospectives for past iterations reveals information organized into columns entitled “What worked for us” and “What did not work for us. ” Based on this information, one can infer that the team did not capture:

A.

user stories

B.

milestones

C.

action items

D.

requirements

Full Access
Question # 17

An Agile team expects a velocity of 8. During sprint planning, the stories were estimatedand prioritized in the following order:

Story A_4Story Points

Story B_2Story Points

Story C_3 Story Points

Story D_2Story Points

Which stories should the team include in Sprint 1, without splitting the stories?

A.

Stories A, C, and D

B.

Stories A, B, and C

C.

Stories A, B, and D

D.

Stories B, C, and D

Full Access
Question # 18

Which term best describes an Agile project's approach to risk analysis?

A.

Regression

B.

Pareto

C.

Qualitative

D.

Monte Carlo

Full Access
Question # 19

Which of the following best represents both a principle of the Agile manifesto and a Lean method of simplicity?

A.

Maximizing the amount of work not done

B.

Delivering early and continuously

C.

Welcoming changing requirements

D.

Deciding at the last responsible moment

Full Access
Question # 20

A business analyst has identified a new risk in an Agile project. What is the best first step the business analyst should take regarding this risk?

A.

Call a meeting with the project manager and senior management to determine how the risk will be managed.

B.

Email the project manager and add it to the risk register so that it is discussed during the next daily standup.

C.

Add the risk in a clearly visible location and ensure it is discussed after the next daily stand up.

D.

Call an immediate meeting with all team members to discuss the newly identified risk.

Full Access
Question # 21

What is the responsibility of an extreme Programming (XP) customer role?

A.

Testing the daily increments of the software developed

B.

Writing the stories and acceptance tests for each story

C.

Planning and task allocation for the developer and tester

D.

Interacting closely with users and representing the XP team

Full Access