Searching for workable clues to ace the Scrum SMC Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s SMC PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 17

Scrum facilitates flexibility through transparency, inspection, and adaptation to ultimately achieve the most valuable business outcomes. All of the following characteristics of Scrum help in achieving flexibility, EXCEPT:

A.

Iterative product development

B.

Cross-functional teams

C.

Continuous stakeholder involvement

D.

Time-boxing

Full Access
Question # 18

Mark is a member of a Scrum Team responsible for testing the code in an ongoing Sprint. Andy, the Product Owner, reassigns him to another project that needs a tester. What should Mark do in a scenario like this?

A.

Inform the Product Owner of the situation, who may extend the deadline for the current Sprint.

B.

Inform the Scrum Master of the situation, who should assign Mark's current task to someone else in the team.

C.

Inform the Scrum Master of the situation, who may discuss the situation with Andy.

D.

Inform the Product Owner of the situation, so that Mark's incomplete task is moved to the next Sprint.

Full Access
Question # 19

Which of the following represents the ideal size for a Scrum Team?

A.

More than 20 members

B.

10 to 20 members

C.

6 to 10 members

D.

1 to 5 members

Full Access
Question # 20

As a Scrum Master, you must be familiar with the Risk Assessment Techniques that are used to assess the likelihood and impact of risks on a project. Select the inappropriate Risk Assessment Technique pairing with its salient qualities.

A.

Expected Monetary Value: Product of monetary impact and risk's probability.

B.

Pareto Analysis: Ranks risks by magnitude.

C.

Probability Impact Grid: Values of potential events are used to calculate the overall impact of risk occurrence.

D.

Probability Trees: A branch for each possible outcome of potential events is represented on a graph.

Full Access
Question # 21

Which of the following is true with respect to maintaining stability in a Scrum project?

A.

The Scrum Master and the Scrum Team should ensure non-interference or changes during a Sprint.

B.

The Sponsor should allow creation of Change Requests and approve them to be incorporated during the ongoing Sprint to avoid unexpected rework later.

C.

The Scrum Team should ensure that complete stability is obtained with the help of iterative delivery and other Scrum characteristics and principles.

D.

Any kind of Change Request can be approved only by the Product Owner.

Full Access
Question # 22

It is the responsibility of the Scrum Master to make sure that all environmental obstructions that may affect the quality of deliverables/processes are eliminated. In this respect, the Scrum Master acts as a:

A.

Leader

B.

Pacifier

C.

Escalator

D.

Facilitator

Full Access
Question # 23

The Scrum Master can help the Product Owner maintain and update a list of Accepted Deliverables after each Sprint Review Meeting. In this regard, which of the following statements is true?

A.

If a deliverable does not meet the defined Acceptance Criteria, it is not considered accepted, and it cannot be carried forward into a subsequent Sprint to rectify any issues.

B.

The objective of a Sprint is to create potentially shippable deliverables that must meet the Acceptance Criteria defined by the Scrum Master.

C.

If a deliverable does not meet the defined Acceptance Criteria, it is not considered accepted, and it will usually be carried forward into a subsequent Sprint.

D.

The objective of a Sprint is to create potentially shippable deliverables that may meet the Acceptance Criteria defined by the customer and Product Owner.

Full Access
Question # 24

Which of the following is NOT the goal of a self-organizing team?

A.

Find solutions for problems raised during Daily Standups after the Standup Meeting.

B.

Complete tasks during a Sprint.

C.

Create a Project Vision that can guide the project.

D.

Accomplish tangible results at the end of each Sprint.