Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

SAFe-Practitioner Exam Dumps - SAFe Practitioner Exam (6.0)

Go to page:
Question # 9

Why is it important to decouple deployment from release?

A.

To allow early access to specific groups of customers

B.

To make deploying of assets a business decision

C.

To remove the need to respond quickly to production issues

D.

To enable releasing functionality on demand to meet business needs

Full Access
Question # 10

Which of the following statements describes the balanced Agile testing pyramid?

A.

Many small, low-level, automated tests & fewer large, manual tests

B.

Many solution tests run by internal team members & fewer run by external testers

C.

Many solution tests run by external testers and fewer run by internal team members

D.

Many large, manual tests of the end-to-end solution and fewer small, automated tests

Full Access
Question # 11

What is the focus of Lean Thinking?

A.

Reducing delays

B.

Implementing objective measures of progress

C.

Ensuring respect for people and culture

D.

Moving to an iterative development process

Full Access
Question # 12

What is one way to understand WIP in a system?

A.

Pair to complete the work faster

B.

Make current work visible

C.

Split stories

D.

Size stories smaller

Full Access
Question # 13

Team A is a maintenance team that cannot always predictably plan their work. They like to meet daily to review the needs of the system and plan for how they can quickly address those needs during the workday. Which of the following SAFe Lean-Agile methods should Team A use to plan and execute their work?

A.

SAFe Platform Team

B.

SAFe Enabling Team

C.

SAFe Team Kanban

D.

SAFe XP Team

Full Access
Question # 14

During the final plan review, ART PI risks are ROAM'ed. What do the letters in ROAM represent?

A.

Resolved, Owned, Approved, Mitigated

B.

Resolved, Owned, Accepted, Mitigated

C.

Resolved, Owned, Assigned, Mitigated

D.

Resolved, Owned, Active, Mitigated

Full Access
Question # 15

Which Lean budget Guardrail helps ensure the appropriate allocation of budgets to balance near-term opportunities with long-term strategy and growth?

A.

Applying capacity allocation

B.

Guiding investments by horizon

C.

Approving significant initiatives

D.

Continuous Business Owner engagement

Full Access
Question # 16

What is one component of the Continuous Delivery Pipeline?

A.

Continuous Exploration

B.

Continuous Cadence

C.

Continuous Planning

D.

Continuous Improvement

Full Access