Searching for workable clues to ace the PeopleCert MSP-Foundation Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s MSP-Foundation PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 9

Which of these is a focus of the ‘embed the outcomes’ process?

A.

To control the work required to manage each tranche of delivery

B.

To maintain an acceptable balance between delivery, transition, realization of benefits, and affordability

C.

To identify when the work has been completed as planned

D.

To realize and measure benefits

Full Access
Question # 10

How does the ‘knowledge’ theme apply the principle ‘lead with purpose’?

A.

By encouraging a culture of continual improvement demonstrating the value added by programme management

B.

By giving knowledge to people, so that teams from multiple organizations work effectively together

C.

By making knowledge as clear as possible so that teams can adapt to new experiences

D.

By effectively creating and sharing knowledge, so that everyone can do their best work

Full Access
Question # 11

Which describes the ‘plan’ phase of the Plan-Do-Check-Act cycle?

A.

It includes steps such as prioritizing an issue or risk

B.

It understands the current programme environment

C.

It validates results and identifies any further actions required

D.

It applies revised actions to reflect changing priorities

Full Access
Question # 12

Which activity occurs during the ‘design the outcomes’ process?

A.

A plan is developed to ensure that capability is delivered at an appropriate pace

B.

Each individual benefit is described in a detailed benefits profile

C.

The programme mandate is developed into a coherent programme brief

D.

A plan is designed of how the outcomes will be achieved through delivery of projects

Full Access
Question # 13

Which document provides a schedule of organizational change activities?

A.

Assurance plan

B.

Stakeholder engagement and communications plan

C.

Benefits realization plan

D.

Financial plan

Full Access
Question # 14

Which document identifies activities to give confidence to stakeholders about how programme risks are managed?

A.

Assurance plan

B.

Financial plan

C.

Benefits realization plan

D.

Stakeholder engagement and communications plan

Full Access
Question # 15

Which process ensures that all facts are available when they are required by the programme board?

A.

Design the outcomes

B.

Plan progressive delivery

C.

Evaluate new information

D.

Close the programme

Full Access
Question # 16

Which TWO are objectives of the ‘design the outcomes’ process?

    To ensure that there is a clear, compelling vision, set out in the vision statement.

    To ensure high-level costs, funding and cash-flow implications have been considered.

    To ensure the delivery approach and ways of working are defined.

    To ensure the target operating model is in place, along with key performance measures.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access