Searching for workable clues to ace the CIPS L6M8 Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s L6M8 PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps
Below are details of 5 companies who are all embarking on the launch of a new product. For each company, you must decide which innovation tactic they are using and the priority for the new contract.
Company 1: The company aims to design the specification around customers’ requirements. They are keen to ensure a balance between costs and the service provided.
Company 2: This company attends regular conferences held by a professional body and will use the information discussed to inform upon the specification. They are keen to ensure sufficient interest from the marketplace so are placing a priority on networking at the conferences.
Company 3: There is a small group of internal stakeholders who meet regularly at Company 3 who discuss supply chain and organisational integration. The priority for the group is to ensure that the supplier of the new product’s raw materials meets the company’s standards for environmental protection.
Company 4: This company has regular phone calls with suppliers discussing ideas for the new product. Once the product is launched, the focus will be on ensuring that the supplier is held to account.
Company 5: Equipment has been loaned to a supplier to produce a prototype of the new product. The aim of the project is to ensure the supplier is capable of producing the components required for the product before the contract is signed.
Complete the table below by listing the innovation tactic and contract priority for each company; focus group, innovation council, technology transfer, collaboration, supplier forum, early supplier involvement, supplier development, balanced scorecard, contract management, selection, value for money, bidding.
Which of the following will you put into box 7?
TGY Ltd is a manufacturing organisation which produces five major components for use in the transport sector. Each component is produced by a different Project Team. Below are details of the five projects.
Project 1: The team are looking at where the material originates and how much of this natural resource is left in the ground.
Project 2: The team are focused on what happens when the product is no longer required by the customer and whether the product can be repurposed to save it going to landfill.
Project 3: The team are keen to ensure the customer is happy with the product and that it meets safety standards. The focus of the Life Cycle Analysis is on what happens inside the factory.
Project 4: The team are looking at the longevity of the item once purchased by the customer.
Project 5: The team are exploring the additional overhead costs associated with the production of the item and the way in which the item is produced.
Complete the table below by listing the area of life cycle analysis being looked at, and the area of the Balanced Scorecard this relates to (some options may be used twice); energy consumption, use, disassembly, extraction, manufacturing, transportation, sustainability x2, quality, environment, value for money, processes.
Which of the following will you put into box 10?
Paula is the Financial Controller for a Consultancy Organisation which operates in the Charity Sector. She is in the process of implementing a spend analysis with the aim to have a higher level of visibility over the company ' s financial data. Which of the following would this allow Paula to do?
Swift Manufacturing is currently seeking new suppliers to create a new product that will be launched next year. They are keen to enter a new market and expand their customer base and ensure the new product provides value for money to the customer. The procurement department is currently conducting market research which will inform upon possible designs for the new product.
Simultaneously they are also speaking with suppliers regarding the specification. Swift Manufacturing are keen to ensure the new product is as environmentally friendly as possible, so are researching different raw materials that can be used and their impact upon the environment.
When designing the tender process, Swift Manufacturing would like the successful supplier to have an environmental management system in place and will incorporate this as part of the ‘essential criteria’ of the specification and tested on the PQQ stage of the tender.
It is important for the CEO of Swift Manufacturing that the supplier hits the ground running on this contract as soon as it is signed, given the importance of the new product to the organisation’s competitive advantage strategy. He is therefore keen to ensure that the procurement department include strict performance targets within the contract.
What approach is being taken with regards to the writing of the specification?
The costs associated with inspection and testing of products to ensure they meet statutory requirements is known as what type of cost?