Question # 4

The average length of time a job must wait at a work center is a function of the:

A.

operation duration.

B.

estimated start date.

C.

planned size of the queue.

D.

transportation time to the work center.

Full Access
Question # 5

Which of the following persons has direct responsibility for the accuracy of production activity reporting?

A.

Controller

B.

Shop supervisor

C.

Materials manager

D.

Director of manufacturing

Full Access
Question # 6

Which of the following applications is an effective use of electronic data interchange?

A.

Routing

B.

Price increase

C.

Advance shipment notice

D.

Returned material authorization

Full Access
Question # 7

The primary reason for using an empty conveyance container as a triggering signal is to:

A.

communicate the need for material.

B.

keep the original container filled with material.

C.

pull material downstream.

D.

push material downstream.

Full Access
Question # 8

A factory is at capacity in a period of stable demand. Which of the following actions would be best to maintain the competitive advantage when product variety is expected to increase?

A.

Establish additional factories.

B.

Increase capacity.

C.

Reduce takt time.

D.

Apply single-minute exchange of die (SMED)

Full Access
Question # 9

Objectives of implementing a work cell include which of the following outcomes?

A.

Increasing worker satisfaction

B.

Organizing resources by raw material type

C.

Implementing standard work

D.

Sharing common equipment

Full Access
Question # 10

A reduction in the lead time results from which of the following actions?

A.

Increase in work-in-process, increase in throughput

B.

Increase in work-in-process, decrease in throughput

C.

Decrease in work-in-process, increase in throughput

D.

Decrease in work-in-process, decrease in throughput

Full Access
Question # 11

The utilization of a downstream nonbottleneck resource is determined by:

A.

a bottleneck resource.

B.

theoretical capacity.

C.

available capacity.

D.

standard hours available.

Full Access
Question # 12

Which of the following statements about the MRP due date for a shop order is true?

A.

It is the same as operation priority.

B.

It is used in deriving operation priority.

C.

It is established at order release time and frozen until order completion.

D.

It is equal to the due date plus 5 "M" days.

Full Access
Question # 13

During the define phase of a six sigma project, which of the following activities takes place?

A.

Describe and chart the process being considered

B.

Determine the possible failure modes

C.

List the proven root causes of the problem

D.

Determine the scope of the project

Full Access
Question # 14

The next job to be performed was selected because it had the least amount of operation time prior to the due date. Which of the following priority sequencing rules was being used?

A.

Slack time per operation

B.

Shortest operation time

C.

Critical ratio

D.

Slack time per order

Full Access
Question # 15

Which of the following methods is used to control variation to improve product quality?

A.

Short-cycle manufacturing

B.

Cycle counting

C.

Buffering inventory

D.

Design for manufacturability