Searching for workable clues to ace the Exin CDFOM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CDFOM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 9

Job descriptions need to be created.

What is the main purpose for doing so?

A.

To provide employees a view on their salary development

B.

To provide employees with clarity on their job scope

C.

To provide employees with an understanding of their career progression

D.

To provide employees with information on possible early retirement

Full Access
Question # 10

A recent cooling equipment failure resulted in a sudden shutdown of IT systems. Although the service provider was quickly on-site, it eventually took more than 12 hours for the cooling equipment to be repaired. Management wants to prevent this from happening again.

What is the best response?

A.

Upgrade to a Time & Material contract

B.

Upgrade to a basic contract

C.

Upgrade to a comprehensive contract

D.

Upgrade to an exclusive contract

Full Access
Question # 11

Which types of maintenance service offerings are commonly offered by vendors?

A.

Silver, Gold, Platinum

B.

Basic, Premium, Premium +

C.

Basic, Normal, Comprehensive

D.

Time & Material, Basic, Comprehensive

Full Access
Question # 12

Who is accountable for the outcome of a project?

A.

The project manager

B.

The user/customer

C.

The business

D.

The supplier

Full Access
Question # 13

During what project phase do you need to start involving the stakeholders?

A.

Initiating the project

B.

Planning the project

C.

Executing the project

D.

Monitoring and control the project

Full Access
Question # 14

What is the outcome of a risk evaluation process?

A.

The decision whether risk treatment needs to take place

B.

The report advising the board of management to accept all identified risks

C.

The list of all identified risks

D.

The required budget treating the data center risk

Full Access
Question # 15

Welding works need to be conducted.

Is a Permit to Work (PTW) required and if so, what type of PTW?

A.

Welding is covered under standard maintenance work, a PTW is not required

B.

A PTW is required for energy work

C.

A PTW is required for cold work

D.

A PTW is required for hot work

Full Access
Question # 16

What describes the term predictive maintenance?

A.

Routine, time or count-based maintenance

B.

Just-in-time maintenance based on monitoring equipment performance

C.

Scheduled maintenance based on history of failure within the site

D.

Maintenance performed upon detection of potential issues