Question # 4

Identification of Mandatory Dependencies is done during which of the following process:

A.

Sequence Activities

B.

Develop Schedule

C.

Define Activities

D.

Estimate Activity Durations

Full Access
Question # 5

Your company create software products, and introducing a new product. To determine the characteristics and features of the new product line, you will have to perform ________.

A.

Progressive elaboration

B.

Stake holder's review

C.

p'an project life cycle

D.

Fast backing

Full Access
Question # 6

A Project Manager is at the project kick-off meeting. He confidently states the vision and mission for the project. This PM is exhibiting the following leadership style:

A.

Hierarchal

B.

Authoritarian

C.

Charismatic

D.

Associative

Full Access
Question # 7

When should a project manager be assigned to a project?

A.

As early in the project as feasible.

B.

Preferably before much project planning has been done.

C.

At least prior to the start of project plan execution.

D.

All of the above.

Full Access
Question # 8

The primary output of the project closing process ____________.

A.

To formalize and distribute all information pertaining to the project closing

B.

Lessons learned

C.

To get customer and sponsor approval

D.

Milestone list

Full Access
Question # 9

Stakeholder influence is greatest at the ______ of the project.

A.

Beginning

B.

Closing

C.

Controlling

D.

Executing

Full Access
Question # 10

A Resource Leveling is a technique for:

A.

Develop Schedule

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Full Access
Question # 11

Which of the following is an output of Define Scope?

A.

PBS

B.

Project Scope statement

C.

WBS Template

D.

Constraints

Full Access
Question # 12

Information should be communicated to __________.

A.

Everyone in the communication plan

B.

Everyone on the team

C.

Sponsor

D.

Team 'eacl

Full Access
Question # 13

Which of the following is a common characteristic of most project life cycle descriptions?

A.

Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.

B.

The probability of successfully completing the project is highest at the start of the project.

C.

Stakeholders have the most influence on the final characteristics of the product at the end of the project.

D.

a and b

Full Access
Question # 14

You are working with an organization and you found that one stakeholder not disclosing all of the costs involved with an upcoming project. Rather, this CAPM is constructing a WBS that does not include all the tasks necessary to get the project done. What you should do?

A.

Talk to the CAPM about the WBS to see if you can rework it to reflect actual costs of the project

B.

Confront the other project manager immediately

C.

Mail t0 PMI headquarters

D.

Ignore it

Full Access
Question # 15

Which process must occur after a project manager has been assigned to the project?

A.

Collect Requirements

B.

Develop the project charter

C.

Develop the project statement of work

D.

Develop project closing document

Full Access
Question # 16

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

Full Access
Question # 17

A major assumption of all network scheduling methods is that the activity duration must be _____.

A.

Statistically dependent

B.

Variance distributed

C.

Statistically independent

D.

Deterministic

Full Access