Question # 17

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

A.

To simplify the structure of bills of material

B.

To reduce the number of changes required in bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To increase the number of planning levels

Full Access
Question # 18

Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

A.

The quantity and value updates are the same.

B.

The same batch management level is used.

C.

The same base unit of measure is used.

D.

The same account category is used.

Full Access
Question # 19

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

A.

First in first out (FIFO)

B.

Simultaneous

C.

Manual maintenance

D.

100% check

Full Access
Question # 20

How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.

A.

By material type

B.

By plant

C.

By period

D.

By material status

Full Access
Question # 21

Which time elements does MRP consider in backward scheduling to determine the basic dates for components from dependent requirements? Note: There are 2 correct answers to this question.

A.

Planned delivery time

B.

Total replenishment lead time

C.

Operation duration

D.

In-house production time

Full Access
Question # 22

Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

A.

Production orders

B.

Planned orders (firmed)

C.

Planned orders (unfirmed)

D.

ATP quantities

Full Access
Question # 23

What are some SAP-recommended guiding principles to achieve clean core operations? Note: There are 3 correct answers to this question.

A.

Establish an organizational structure, technical foundation, and transformation methodology for clean core.

B.

Integrate clean core practices in the end-to-end value process chain.

C.

Establish release management.

D.

Establish regular housekeeping tasks and procedures.

E.

Define roles and responsibilities as part of a process transformation office.

Full Access
Question # 24

What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?

A.

MRP creates a dependent requirement.

B.

A sales order is delivered.

C.

MRP creates a planned order.

D.

A sales order is created.