Searching for workable clues to ace the SAP C_TPLM22_67 Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s C_TPLM22_67 PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 4

What are the three tables that are defined for order type in network costing?

There are 3 correct answers to this question.

Response:

A.

Each order type

B.

Each order type and plant

C.

Network profile

D.

Each plant

Full Access
Question # 5

In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?

Please choose the correct answer.

Response:

A.

Periodic settlement

B.

Full settlement

C.

Profile settlement

D.

Overview settlement

Full Access
Question # 6

Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?

There are 2 correct answers to this question.

Response:

A.

Activate milestone functions.

B.

Activate indicator sales document date for milestones.

C.

Create a billing plan assigned to a sales order item.

D.

Set up percentage of completion for milestones.

E.

Create a billing plan assigned to a WBS element.

Full Access
Question # 7

With reference to material requirements in Project System (PS-MAT), which of the following statements are true?

Please choose the correct answer.

Response:

A.

9999 components may be created per network.

B.

Project System supports consignment stock.

C.

Component scrap is considered during BOM explosion.

Full Access
Question # 8

In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks?

There are 2 correct answers to this question.

Response:

A.

Project scheduling

B.

Overall network scheduling

C.

Network scheduling

D.

Forward scheduling

Full Access