Searching for workable clues to ace the Adobe AD0-E911 Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s AD0-E911 PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 9

A user wants to notify a team of a new work request for them to work on.

Where would the user set the team so they are notified of the new work request?

A.

Request > Request Details

B.

Request > Updates

C.

Request > Assignments

Full Access
Question # 10

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

A.

Visit the Project page and create a new filter. Update the " Pending Approval " filter to " true " and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.

B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the " Pending Approval " filter to " true, " and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.

C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to " tasks " and " issues. " In the grouping tab, add a grouping for project name.

Full Access
Question # 11

Which date type should an assignee update to change the completion date of a task?

A.

Actual Completion Date

B.

Commit Date

C.

Planned Completion Date

D.

Projected Start Date

Full Access
Question # 12

A project manager is updating a project in Workfront that is behind schedule.

Which action could be taken so that all tasks are completed by the requested completion date?

A.

Give all tasks a Task Constraint of “Must Start On”

B.

Reduce the durations of the tasks.

C.

Adjust all of the Planned Start Dates to the same day.

Full Access
Question # 13

What do the green symbols in the report below signify?

A.

On Time

B.

At Risk

C.

Late

Full Access
Question # 14

A project manager would like to assign tasks across projects to a team without having to navigate to each project.

How can the project manager do this?

A.

Assign work using the Resource Planner.

B.

Assign work by drag-and-drop.

C.

Assign work in bulk.

Full Access
Question # 15

A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.

Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?

A.

Four reports showing the entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, a third report that shows recently completed requests, and a fourth report that shows the schedule assigned to each team member.

B.

Two reports showing the priority and actual completion date of each request, i.e., one that shows active requests and another that shows recently completed requests.

C.

Three reports showing the priority and entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, and one that shows recently completed requests.

Full Access
Question # 16

To whom or what would a project owner assign a task so the task is visible in a Scrum or Kanban backlog?

A.

A user that has access to a burndown

B.

A job role labeled as Agile User

C.

A team marked as an agile team

Full Access